PERT est une méthodologie de gestion de projet. Il s'agit d'un fork du programme bash qui permet d'afficher les tâches et les prévisions individuels et cumulés : https://github.com/arzzen/pert
Ви не можете вибрати більше 25 тем Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
Lukáš Mešťan 2b6419639b
Update LICENSE
4 роки тому
.github Create FUNDING.yml 4 роки тому
CODE_OF_CONDUCT.md Create CODE_OF_CONDUCT.md 6 роки тому
CONTRIBUTING.md Create CONTRIBUTING.md 6 роки тому
LICENSE Update LICENSE 4 роки тому
Makefile makefile 8 роки тому
README.md Update README.md 7 роки тому
pert piping added and resolved the conflicts 7 роки тому

README.md

Bash PERT Calculator

A simple utility to estimate tasks using PERT (Program evaluation and review technique)

Demo

pert example

Usage

Comma separated task list in the form "1,2,12 4,5,9 2,3,6", where whitespace separates tasks. (or you can use piping inputs echo "1,2,3 10,30,40" | pert)

Usage:

pert [optimistic,realistic,pessimistic]

Example:

pert 1,3,4

pert 10,15,20 5,7,10

pert "1,2,3" "15,17,20"

cat data.txt | pert

echo "1,2,3 9,10,14" | pert

Install

$ git clone https://github.com/arzzen/pert.git && cd pert
$ sudo make install

For uninstalling, open up the cloned directory and run

sudo make uninstall

Example

Command:

$ ./pert 5,7,10 2,3,4 10,12,14

Output:

Tasks

+--------------------------------------------------------------------------------------+ | # | optimistic | realistic | pessimistic | duration | risk | variance | +--------------------------------------------------------------------------------------+ | 1. task | 5 | 7 | 10 | 7.16 | 0.83 | 0.68 | | 2. task | 2 | 3 | 4 | 3.00 | 0.33 | 0.10 | | 3. task | 10 | 12 | 14 | 12.00 | 0.66 | 0.43 | +--------------------------------------------------------------------------------------+ | summary | - | - | - | 22.16 | 1.82 | 1.21 | +--------------------------------------------------------------------------------------+

Three point estimates

+----------------------------------------+ | confidence | | | +----------------------------------------+ | 1 Sigma - 68% | 20.34 | 23.98 | | 2 Sigma - 95% | 18.52 | 25.80 | | 3 Sigma - 99% | 16.70 | 27.62 | +----------------------------------------+