+### Bash PERT Calculator
|
|
2
|
+
|
|
3
|
+A simple utility to estimate tasks using PERT (Program evaluation and review technique)
|
|
4
|
+
|
|
5
|
+### Usage
|
|
6
|
+<pre>
|
|
7
|
+A command line PERT calculator for quick estimates.
|
|
8
|
+
|
|
9
|
+Comma separated task list in the form "1,2,12 4,5,9 2,3,6", where whitespace separates tasks.
|
|
10
|
+
|
|
11
|
+Usage:
|
|
12
|
+ pert [optimistic,realistic,pessimistic]
|
|
13
|
+
|
|
14
|
+Example:
|
|
15
|
+ pert 1,3,4
|
|
16
|
+ pert 10,15,20 5,7,10
|
|
17
|
+ pert "1,2,3" "15,17,20"
|
|
18
|
+</pre>
|
|
19
|
+
|
|
20
|
+### Example
|
|
21
|
+
|
|
22
|
+Command:
|
|
23
|
+
|
|
24
|
+`$ ./pert.sh 5,7,10 2,3,4 10,12,14`
|
|
25
|
+
|
|
26
|
+Output:
|
|
27
|
+<pre>
|
|
28
|
+Tasks
|
|
29
|
+
|
|
30
|
+ +--------------------------------------------------------------------------------------+
|
|
31
|
+ | # | optimistic | realistic | pessimistic | duration | risk | variance |
|
|
32
|
+ +--------------------------------------------------------------------------------------+
|
|
33
|
+ | 1. task | 5 | 7 | 10 | 7.16 | 0.83 | 0.68 |
|
|
34
|
+ | 2. task | 2 | 3 | 4 | 3.00 | 0.33 | 0.10 |
|
|
35
|
+ | 3. task | 10 | 12 | 14 | 12.00 | 0.66 | 0.43 |
|
|
36
|
+ +--------------------------------------------------------------------------------------+
|
|
37
|
+ | summary | - | - | - | 22.16 | 1.82 | 1.21 |
|
|
38
|
+ +--------------------------------------------------------------------------------------+
|
|
39
|
+
|
|
40
|
+Three point estimates
|
|
41
|
+
|
|
42
|
+ +----------------------------------------+
|
|
43
|
+ | confidence | | |
|
|
44
|
+ +----------------------------------------+
|
|
45
|
+ | 1 Sigma - 68% | 20.95 | 23.37 |
|
|
46
|
+ | 1 Sigma - 95% | 19.74 | 24.58 |
|
|
47
|
+ | 1 Sigma - 99% | 18.53 | 25.79 |
|
|
48
|
+ +----------------------------------------+
|
|
49
|
+ </pre>
|